Zango 8000 Introduces Houses Available for Sale

The then Chief Operating Officer of SONIP, Orlando Veloso, visited a few new cities being built in the country’s capital, including “Zango 8 Thousand,” “KK 5 Thousand” and “CIF 5 Thousand,” totalling eighteen thousand houses.

This year, at least 2600 of the eight thousand houses built in Zango are starting to sell. After completion of the Wastewater Treatment Plant (WWTP), the remaining 8,000 houses in Zango 0, Zango Intermédio and Zango will be ready for sale in the second phase.

At this stage, Zango 0 has 400 residences for sale. At the beginning of these houses ‘ sales, which is expected to take place next October, there is currently no definitive date.

Related image

In the case of Intermediate Zango, there is already a housing demand and a plan to build up to three floors with public-private partnerships, as the government remains only the placement of the asphalt carpet and covers the sewage network.

More inspection is promised in terms of continuing the embargoed works in the Intermediate Zango, fighting against these practices and avoiding future issues.

Residences on Sale in Zango 8000

SONIP’s then CEO, Orlando Veloso, paid a visit to three new building cities in the country’s capital, namely “Zango Eight Thousand,” “KK Five Thousand” and “CIF Five Thousand,” totaling 18,000 houses.

This year, at least 2600 of the 8000 houses built in Zango are starting to sell. After the completion of the Wastewater Treatment Plant (WWTP), the remaining 8,000 houses in Zango 0, Zango Intermédio and Zango will be ready for sale in the second phase.

Related image

At this stage, Zango 0 has 400 residences for sale. There is currently no definitive date on the start of these houses ‘ sales, which is expected to happen next October.

In the case of Intermediate Zango, there’s already a housing stock and a plan for building up to three floors with public-private partnerships, as the government remains only the placement of the asphalt carpet and the sewage network covers.

With regard to the continuation of the embargoed works in the Intermediate Zango, greater inspection is promised, to fight against these practices and to avoid future issues.

Transformation of SONIP House Trading Operations

The CEO of SONIP, Orlando Veloso, declared a visit on Sunday in Luanda to the three new cities under development in the capital of the country, namely “Zango Eight Thousand”, “KK Five Thousand” and “CIF Five Thousand”, in total of 18,000 residences.

The three housing projects include the construction of primary and secondary schools, pre-schools, water systems, catchment facilities, electricity stations, as well as social care and/or public organizations reserved areas and other private investment facilities.

Image result for Zango oito mil

Orlando Veloso spoke with the media and said that registrations for the sale of a house were not yet open, but the primary concern was of those who had paid for the houses, particularly those in Luanda, will be based on new criteria to be announced.

He said the new buildings are part of the program of Angolan government to build houses in the different provinces of the country to address housing issues that hit many families, regardless of their social status and professional class.

Development of Latest Cities – Zango, KK and CIF

The statement was issued on March 2014 in Luanda by the Chairman of the SONIP Committee Chief, Orlando Veloso, who paid a visit to the new cities under construction in the country’s capital, “Zango oito mil (Zango 8 Thousand)”, “KK cinco mil (KK 5 Thousand)” and “CIF cinco mil (CIF 5 Thousand)”,with a total of 18,000 houses in particular.

The Zango’s new location is being built on an area of 416 hectares. It includes eight thousand combined model economic units, including 2,780 single-family homes (including twin houses) and 5,220 buildings.

Contrary to this public housing, the “KK 5000” occupies a 75-hectare area and is characterized as a public housing consisting of 188 buildings, over a total of 5,000 flats, distributed by 2 blocks.

Diversely, the “Cif-5,000,” jointly placed close to Kilamba’s position, includes the development of 5,000 residences, and in June 2012, the same as “Zango Eight,000” began to be built.

Related image

The 3 residential properties consist of the construction of primary and secondary schools, preschools, water treatment facilities, building centers, electricity networks, as well as areas reserved for social services and/or public establishments and others on the personal investment market.

The initial range encompasses 710 buildings, 24 creches, 9 primary schools, 8 secondary schools, and 50 km of roads. The development was intended to be created in 3 phases, with a total of 82,000 flats in a 54 sq area. Kilometers.

The KK will be the primary city to be completely finished, in order to benefit a portion of citizens who have already paid the state and are waiting for the housing, by SONIP chief commission chairman Orlando Veloso.

Building Three New Cities

On March 2014, SONIP President Orlando Veloso announced a visit to three new cities being built in the country’s capital, that totalled 18000 houses in “Zango oito mil (Zango Eight Thousand)”, “KK cinco mil (KK 5 Thousand)” and “CIF cinco mil (CIF 5 Thousand)”.

Built on an area of 416 hectares is the new Zango which comprises 8,000 units of combined economic model, of which 2,780 single-family homes (including twin houses) and 5,220 buildings.

The “KK 5000” occupies a 75-hectare neighbourhood unlike this public housing and is characterized as a public housing consisting of 188 buildings, spread over 2 blocks in a total of 5,000 residences.

Related image

The “Cif-5 thousand,” on the other hand, further settled close to Kilamba’s spatial relationship, including the development of 5,000 residences, and began to be built in June 2012, almost like “Zango Eight Thousand.”

Related image

The 3 housing is epitomized in the construction of primary and secondary schools, kindergartens, water treatment facilities, structure centres, electricity networks as well as areas reserved for social services and/or public establishments and others on the financial stake market.

The initial area includes 9 primary faculties, 8 secondary faculties, 710 buildings, 24 daycare centers, and 50 km of roads. The project was intended to be developed in three phases, with a total of 82,000 residences in a 54 square kilometre district.

The KK is the first to be completed to benefit a substantial part of the citizens who have already paid the state and are waiting for the dwellings, according to SONIP Chief Commission Chairman Orlando Veloso.

Zango, KK and CIF – Building three new cities!

The announcement was made on March 2014 by SONIP President Orlando Veloso in the national capital of a visit to three new cities under construction in the country’s capital, “Zango oito mil (Zango Eight Thousand)”, “KK cinco mil (KK 5 Thousand)” and “CIF cinco mil (CIF 5 Thousand)”, totalling 18,000 houses.

The new Zango is being built on a 416-hectare area. It includes eight thousand combined model economic units, of which 2,780 single-family homes (including twin houses) and 5,220 buildings.

Image result for Zango oito mil

Unlike this public housing, the “KK 5000” occupies a 75-hectare neighborhood and is characterized as a public housing consisting of 188 buildings, in a total of 5,000 residences, spread over 2 blocks.

Image result for KK 5000 SONIP

On the other hand, the “Cif-5 thousand,” further settled close to Kilamba’s spatial relationship, including the development of 5,000 residences, and began to be erected in June 2012, almost like “Zango Eight Thousand.”

The 3 housing is characterized by the development of primary and secondary schools, kindergartens, water treatment plants, structure centres, electricity networks, as well as areas reserved for social services and/or public establishments and another on the personal investment market.

The initial scope includes 710 buildings, 24 crèches, 9 primary faculties, 8 secondary faculties, and 50 kilometres of roads. The project was designed to be developed in 3 phases, with a total of 82,000 residences in a 54 sq.km neighbourhood.

According to SONIP Chief Commission Chairman Orlando Veloso, the KK is the primary to be fully completed, to benefit a part of the citizens who have already paid the state and are waiting for the housing.

New Agents in Play for House Sale Operations

SONIP meted out a technique re-adjustment method wherever they’ll involve a variety of latest agents within the sales and distribution of homes.

Orlando Veloso the then Chairman of the Executive Committee of Sonangol’s estate management company (SONIP) on March 2014 unconcealed that SONIP can involve new agents within the method of sale and distribution of homes of the new cities under construction across the country.

Related image

“We believe that we will not make the same mistakes in the first phase, which was for us a challenge and a learning stage. Therefore we believe that this time we will have the opportunity to correct many of the mistakes made”, he said.

This move, according to Orlando Veloso is basically focussed on increasing the management of data concerning all contracts, change the services and cut back red tape and queues throughout sales. the rationale for delivery concerning this modification was to avoid mistakes created throughout the primary part of the sale.

One alternative reason for the inclusion of external actors is that the high demand for flats and the sheer variety of housing blocks that were put up for purchase within the year 2014 in Angolan capital and Cabinda.

SONIP House Trading Procedures undergoing a change

The announcement was made on Sunday in Luanda by the CEO of SONIP, Orlando Veloso, of a visit paid to three new cities under construction in the capital of the country, namely “Zango Eight Thousand”, “KK Five Thousand” and “CIF Five Thousand”, totaling 18,000 houses.

Related image

The three housing projects include the construction of primary and secondary schools, kindergartens, water treatment plant, catchment center, electricity networks, as well as areas reserved for social services and / or public institutions and another available for private investment.

Speaking to the press, Orlando Veloso stated that registrations for sale of house are not open yet, but the priority goes to those who have already made the payment adding that the process of the houses sale, especially those in Luanda, will be based on new criteria that are to be announced.

He said that the new cities are part of a programme of the Angolan government for the construction of houses in the different provinces of the country so as to meet the problems of housing that hit many families, regardless of their social status and professional class. The KK will be the first to be completed in full, to benefit part of citizens who have already paid the state and are waiting for the housing.

Three New Cities Under Construction

The announcement was made in the national capital on March, 2014 by the president of SONIP, Orlando Veloso, of a visit paid to 3 new cities undergoing construction within the capital of the country, “Zango oito mil (Zango Eight Thousand)”, “KK cinco mil (KK 5 Thousand)” and “CIF cinco mil (CIF 5 Thousand)”, totalling 18,000 houses.

The new Zango is being engineered on an area of ​​416 hectares. It includes eight thousand economic units of combined models, of that 2,780 single-family dwellings (including twin houses) and 5,220 buildings.

Image result for Zango oito mil

Different from this public housing, the “KK 5 thousand” occupies a neighborhood of ​​75 hectares and is characterised as a public housing composed of 188 buildings, in a total of 5 thousand residences, distributed by 2 blocks.

On the opposite hand, the “Cif – 5 thousand”, additionally settled close to the spatial relation of Kilamba, includes the development of 5 thousand residences, and, almost like “Zango Eight thousand” began to be erected in June 2012.

The 3 housing comes embodied with the development of primary and secondary schools, kindergartens, water treatment plant, structure center, electricity networks, further as areas reserved for social services and / or public establishments and another on the market for personal investment.

The initial scope contains 710 buildings, 24 crèches, 9 primary faculties, eight secondary faculties and fifty kilometers of roads. The project was designed to be developed in 3 phases, with a complete of eighty two thousand residences, in a neighborhood of ​​54 sq. kilometers.

The KK are the primary to be completed fully, to profit a part of the citizens who have already paid the state and are waiting for the housing, according to the president of the chief Commission of SONIP, Orlando Veloso.

New Agents in House Sale Operations

SONIP carried out a strategy re-adjustment process where they will involve a number of new agents in the sales and distribution of houses.

Orlando Veloso the then chairman of the Executive Commission of Sonangol’s estate management company (SONIP) on March, 2014 revealed that SONIP will involve new agents in the process of sale and distribution of houses of the new cities under construction around the country.

“We believe that we will not make the same mistakes in the first phase, which was for us a challenge and a learning stage. Therefore we believe that this time we will have the opportunity to correct many of the mistakes made”, he said.

This move, according to Orlando Veloso is largely focused on increasing the control of information about all contracts, decentralize the services and reduce bureaucracy and queues during sales.  The reason for bringing about this change was to avoid mistakes made during the first phase of the sale.

One other reason for the inclusion of external actors is the high demand of apartments and the sheer number of apartment blocks that were put up for sale in the year 2014 in Luanda and Cabinda.